The Mercedes-Benz Places tower in Downtown Dubai has reached approximately 65 percent completion, with structural work now past the 52nd floor of its planned 65 stories. Developed by Binghatti in collaboration with Mercedes-Benz, the 341-meter elliptical tower remains on schedule for handover in the final quarter of 2026. Recent audits confirm steady vertical progress on the Sheik Zayed Road site, where the building’s distinctive curved form is already legible against the skyline.

What Has Already Risen
The core and primary structural frame have advanced well beyond the halfway mark. Floor plates continue to be cast in sequence, and the distinctive elliptical geometry is now visible from street level and surrounding towers. The continuous curved profile, the element most closely associated with Mercedes-Benz’s aerodynamic design language, is no longer limited to renderings. It is concrete, steel, and formwork rising in measured increments.
Early façade work has begun on the lower levels. The rear elevation, which will eventually carry approximately 75,000 square feet of building-integrated photovoltaics, is being prepared for the installation of the energy-generating skin. That system is designed to supply power for on-site electric-vehicle charging, targeting the equivalent of 40 full charges per day once operational.
Internally, the high floor-to-ceiling heights of 4.2 meters are already established in the completed structural shells. These proportions, central to the project’s aim of translating automotive spatial luxury into residential form, are being locked in as the tower rises.
What Remains

The upper third of the structure still lies ahead. Roughly 13 floors of primary structure, the crown, and the full envelope remain to be completed. Façade installation across the entire height will be one of the most visible remaining phases, particularly the precise alignment of the curved glass and the photovoltaic array on the rear face.
Interior fit-out has not yet reached full scale. Once the structure is sealed, attention will shift to the installation of the specified material palette (leather, wood, metal and soft neutrals) intended to extend the brand’s design language into the residences. Mechanical, electrical and plumbing systems, vertical transportation, and the full suite of amenity spaces will follow structural completion.

The final months will also include testing and commissioning of the energy systems, mobility infrastructure and resident services that form part of the branded experience.
Design Decisions Now Being Built

Several design choices made at concept stage are now being tested by construction.
The elliptical plan requires continuous precision in formwork and alignment. Unlike orthogonal towers, any deviation becomes immediately visible across the curved surface. The decision to integrate photovoltaics directly into the façade rather than treating them as a rooftop or secondary system means the rear elevation must perform simultaneously as a weather barrier, energy generator, and formal expression.

The high ceiling heights and fluid interior planning place greater demands on structural coordination and services distribution. These requirements are being resolved floor by floor as the building rises.
Even the naming of residences after significant Mercedes models is being carried through into the detailed design documentation, reinforcing the idea that the brand identity is distributed across every level rather than applied only at the entrance.
A Construction Timeline in Real Time

From groundbreaking in late 2023 to 65 percent completion by mid-to-late 2026, the project has maintained a steady vertical pace. The remaining program is tight but still within the original handover window. The coming months will determine whether the precision demanded by the curved geometry and the integrated energy systems can be sustained through the upper floors and the fit-out phase.
For now, the tower stands as a clear mid-construction marker: more than half complete, already asserting its elliptical presence on the Downtown skyline, and still aimed at welcoming its first residents before the end of 2026.